United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Spur Energy Storage

Spur Energy Storage is a 306 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wise County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0278
Grid region
ERCOT (Texas)
Developer
Spur Energy Storage, LLC
Connection point (POI)
Tap 345kV (1429) JACKSBRO_5 - (11736) BIRDDOG_5
Location
Wise County, Texas
Technology
Battery: 306 MW
Total requested
306 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
25 February 2025
Proposed online date
September 2028

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem