United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTConnolly Storage
Connolly Storage is a 125 MW other request built and operating in the ERCOT interconnection queue, in Wise County, Texas.
Request details
- Queue ID
- 23INR0403
- Grid region
- ERCOT (Texas)
- Developer
- BT Connolly Storage, LLC
- Connection point (POI)
- Tap 138kV 1568 Allison βΓΓ¬ 11568 Flatwood
- Location
- Wise County, Texas
- Technology
- Other: 125 MW
- Total requested
- 125 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 26 October 2021
- Agreement signed
- 27 February 2023
- Proposed online date
- November 2024
- Came online
- November 2024
Location
Marker shows the centre of Wise County; the queue data does not give exact sites.
Other requests in Wise County
- Wise County Power Repower (CT1, CT2)Gas Β· 21.0 MW Β· agreement signed
- Gilleys Energy StorageBattery storage Β· 306 MW Β· in study
- Spur Energy StorageBattery storage Β· 306 MW Β· in study
- Solar Star Rhome StorageBattery storage Β· 221 MW Β· in study
- Legato BESSBattery storage Β· 203 MW Β· in study
- Pianissimo BESS IIBattery storage Β· 202 MW Β· in study
- Yooperlite StorageBattery storage Β· 176 MW Β· in study
- Sandford SolarSolar + storage Β· 126 MW Β· in study
- Sandford StorageSolar + storage Β· 101 MW Β· in study
- Pruett SolarSolar Β· 151 MW Β· withdrawn
- Pruett StorageBattery storage Β· 50.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem