United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTSolar Star Rhome Storage
Solar Star Rhome Storage is a 221 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wise County, Texas.
Queue statusIn planning
- PlanningQueued Apr 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0040
- Grid region
- ERCOT (Texas)
- Developer
- Solar Star Rhome Storage
- Connection point (POI)
- 576 RHOME 138kV
- Location
- Wise County, Texas
- Technology
- Battery: 221 MW
- Total requested
- 221 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 19 April 2023
- Proposed online date
- March 2027
Location
Marker shows the centre of Wise County; the queue data does not give exact sites.
Other requests in Wise County
- Wise County Power Repower (CT1, CT2)Gas · 21.0 MW · agreement signed
- Gilleys Energy StorageBattery storage · 306 MW · in study
- Spur Energy StorageBattery storage · 306 MW · in study
- Legato BESSBattery storage · 203 MW · in study
- Pianissimo BESS IIBattery storage · 202 MW · in study
- Yooperlite StorageBattery storage · 176 MW · in study
- Sandford SolarSolar + storage · 126 MW · in study
- Sandford StorageSolar + storage · 101 MW · in study
- Connolly StorageOther · 125 MW · built
- Pruett SolarSolar · 151 MW · withdrawn
- Pruett StorageBattery storage · 50.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem