United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· ERCOT

Pruett Storage

Pruett Storage is a 50.5 MW battery storage request withdrawn in the ERCOT interconnection queue, in Wise County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2022 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0408
Grid region
ERCOT (Texas)
Developer
Crandall Solar LLC
Connection point (POI)
Tap 138kV 587 Greenwood - 685 Leo
Location
Wise County, Texas
Technology
Battery: 50.5 MW
Total requested
50.5 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
24 July 2022
Proposed online date
May 2027
Withdrawn
April 2025

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Wise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem