United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Yooperlite Storage

Yooperlite Storage is a 176 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wise County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0466
Grid region
ERCOT (Texas)
Developer
BT Yooperlite Storage, LLC
Connection point (POI)
Tap 138 kV 580 Westbrook Switch - 588 Willow
Location
Wise County, Texas
Technology
Battery: 176 MW
Total requested
176 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
28 June 2023
Proposed online date
May 2028

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wise County