United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 3 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Euismod
Solar + storage
1,247 MWAgreement signed Kern, CACAISO Apr 2021target 2028
Limitless Energy Hub I
Gas · Limitless Energy Hub I LLC
1,238 MWIn study Wilbarger, TXERCOT Nov 2025target 2028
Limitless Energy Hub II
Gas · Limitless Energy Hub II LLC
1,238 MWIn study Wilbarger, TXERCOT Nov 2025target 2028
Southeast Oklahoma Pumped Storage
Other · Apex Energy Solutions, LLC
1,232 MWIn study Lamar, TXERCOT Aug 2022target 2030
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem
Gas
1,232 MWIn study Iberville, LAMISO May 2024target 2025
Potentia-Viridi
Other
1,225 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Matterhorn
Other
1,218 MWIn study Riverside, CACAISO Apr 2023target 2029
Solstice B
Solar + storage
1,211 MWIn study Fresno, CACAISO Apr 2023target 2031
Red Oak Ridge Energy Center
Gas · Invenergy
1,211 MWIn study Kenosha, WIMISO Aug 2025target 2027
Gas project E0016, Calumet County
Gas · Invenergy
1,211 MWIn study Calumet, WIMISO Aug 2025target 2027
Wolf Bone North Energy Center
Gas · NRG Wolf Bone Energy Center LLC
1,204 MWIn study Reeves, TXERCOT Oct 2025target 2029
Gas project J4164, Dane County
Gas
1,203 MWIn study Dane, WIMISO Sep 2025target 2030
Gas project J4165, Kenosha County
Gas
1,203 MWIn study Kenosha, WIMISO Sep 2025target 2030
Gas project J4014, Calumet County
Gas
1,203 MWIn study Calumet, WIMISO May 2025target 2030
SouthCoast Wind 1
Offshore wind
1,200 MWAgreement signed MAISO-NE Apr 2021target 2031
Solar project G0678, Morrow County
Solar
1,200 MWIn study Morrow, ORWest Jun 2021target 2024
Bay State Wind 4 Offshore Wind
Offshore wind
1,200 MWAgreement signed MAISO-NE Dec 2019target 2033
Solar + storage project G0615, Sherman County
Solar + storage
1,200 MWIn study Sherman, ORWest Feb 2019target 2021
Solar + storage project IC-942, Glynn County
Solar + storage
1,200 MWPaused / redesign Glynn, GASoutheast Mar 2021target 2025
Battery storage project G0608, Klickitat County
Battery storage
1,200 MWIn study Klickitat, WAWest Dec 2018target 2027
Solar + storage project Q105, Millard County
Solar + storage · Intermountain Power Agency
1,200 MWIn study Millard, UTWest Jun 2023target 2028
Spectra Solar
Solar · SE DC Devco
1,200 MWIn study Scurry, TXERCOT Dec 2025target 2028
Corvette Wind
Onshore wind
1,200 MWPaused / redesign Carson, TXERCOT Feb 2024
Other project G0787, Wasco County
Other
1,200 MWIn study Wasco, ORWest Aug 2022target 2028
Solar + storage project G0702, Crook County
Solar + storage
1,200 MWIn study Crook, ORWest Sep 2021target 2025
Aviation
Gas
1,200 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Eagle Pines Gas
Gas · FGE Power
1,174 MWIn study Cherokee, TXERCOT Mar 2015target 2028
Pion
Battery storage
1,168 MWIn study Fresno, CACAISO Apr 2023target 2028
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Gas project J3941, Deuel County
Gas
1,144 MWIn study Deuel, SDMISO Mar 2025target 2030
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Gas project 257, Shelby County
Gas
1,132 MWAgreement signed Shelby, TNSoutheast Aug 2014target 2018
Aurelius Solar
Solar · IP Roman, LLC
1,124 MWAgreement signed Deaf Smith, TXERCOT Jul 2023target 2028
Battery storage project AI2-457, Charles County
Battery storage
1,122 MWIn study Charles, MDPJM Mar 2023target 2027
Nuclear project G0998, Benton County
Nuclear
1,120 MWIn study Benton, WAWest Nov 2023target 2030
Solstice A
Solar + storage
1,111 MWIn study Fresno, CACAISO Apr 2023target 2031
Bastrop Peaking Generators (TEF-Due Diligence)
Gas · MPH Bastrop Peakers, LLC
1,104 MWAgreement signed Bastrop, TXERCOT Feb 2024target 2027
Gas project G0501, Klamath County
Gas
1,100 MWIn study Klamath, ORWest Oct 2014target 2018
Malden CCGT
Gas · NIPSCO
1,090 MWIn study Porter, INMISO Aug 2025target 2028
Mosey
Solar + storage
1,081 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Hillside Energy Storage
Battery storage
1,065 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Musketeers
Solar + storage
1,047 MWIn study Tulare, CACAISO Apr 2023target 2029
Gas project GEN-2024-341, Pittsburg County
Gas
1,045 MWIn study Pittsburg, OKSPP Mar 2025target 2031
Zeus Armstrong BESS
Solar + storage · Armstrong BESS, LLC
1,043 MWIn study Armstrong, TXERCOT Mar 2024target 2028
Zeus Scurry BESS
Solar + storage · Zeus Scurry BESS
1,043 MWIn study Scurry, TXERCOT Jun 2025target 2028
Zeus Mitchell BESS II
Solar + storage · Zeus Mitchell BESS II, LLC
1,043 MWIn study Mitchell, TXERCOT Jun 2025target 2027
Zeus Mitchell BESS
Solar + storage · Mitchell BESS
1,043 MWIn study Mitchell, TXERCOT May 2024target 2029
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2
Gas
1,040 MWIn study Vermillion, INMISO Feb 2024target 2028
Oberon
Solar + storage
1,037 MWAgreement signed Riverside, CACAISO Apr 2019target 2026
Page 3 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)