Solar + storage project IC-942, Glynn County

Solar + storage project IC-942, Glynn County is a 1,200 MW solar + storage request suspended in the Southeast interconnection queue, in Glynn County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-942
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Thalmann TS 500 kV Bus
Location
Glynn County, Georgia
Technology
Solar: 1,200 MW · Battery
Total requested
1,200 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
19 March 2021
Proposed online date
April 2025

Location

Marker shows the centre of Glynn County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Glynn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem