SOLAR Β· SOUTHEASTSolar project IC-700, Glynn County
Solar project IC-700, Glynn County is a 280 MW solar request withdrawn in the Southeast interconnection queue, in Glynn County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedJun 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-700
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Thalmann TS 500 kV Bus
- Location
- Glynn County, Georgia
- Technology
- Solar: 280 MW
- Total requested
- 280 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 10 May 2018
- Withdrawn
- June 2018
Location
Marker shows the centre of Glynn County; the queue data does not give exact sites.
Other requests in Glynn County
- Pepper Hammock 500 SolarSolar Β· 500 MW Β· in study
- Pepper Hammock SolarSolar Β· 200 MW Β· in study
- Pepper Hammock 200 MWSolar Β· 200 MW Β· in study
- Solar + storage project IC-942, Glynn CountySolar + storage Β· 1,200 MW Β· suspended
- Solar + storage project IC-932, Glynn CountySolar + storage Β· 250 MW Β· suspended
- Solar + storage project IC-933, Glynn CountySolar + storage Β· 250 MW Β· suspended
- Gas project IC-007, Glynn CountyGas Β· 620 MW Β· withdrawn
- Gas project IC-220, Glynn CountyGas Β· 613 MW Β· withdrawn
- Gas project IC-102, Glynn CountyGas Β· 553 MW Β· withdrawn
- Gas project IC-101, Glynn CountyGas Β· 553 MW Β· withdrawn
- Gas project IC-076, Glynn CountyGas Β· 550 MW Β· withdrawn
- Gas project IC-107, Glynn CountyGas Β· 508 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem