United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 136
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project G0885, Linn County Other |
80.0 MW | In study |
| Solar + storage project C2-09, Crook County Solar + storage · SSEV D LLC |
80.0 MW | Agreement signed |
| Solar + storage project IC-1060, Marengo County Solar + storage |
80.0 MW | Paused / redesign |
| Solar project 564510, Bladen County Solar |
80.0 MW | Agreement signed |
| Solar project AG2-568 Solar · Sundial Energy, LLC |
80.0 MW | In study |
| Solar project 781, Tooele County Solar · Elektron Solar, LLC |
80.0 MW | Agreement signed |
| Surplus; Old Gold Other |
80.0 MW | In study |
| Other project PP00035, Wilson County Other |
80.0 MW | In study |
| Solar project J2917, Ouachita Parish County Solar |
80.0 MW | In study |
| Solar + storage project TCS-03, Adams County Solar + storage |
80.0 MW | Paused / redesign |
| Walker Solar Two Solar |
80.0 MW | Agreement signed |
| Other project PP00051, Duplin County Other |
80.0 MW | In study |
| Solar + storage project PIS100, Crook County Solar + storage |
80.0 MW | In study |
| Battery storage project AG2-518, Montgomery County Battery storage · Delorean Power LLC dba Lightshift Energy |
80.0 MW | In study |
| Solar project AH1-666, Fleming County Solar · Fleming Solar, LLC |
80.0 MW | In study |
| Wind + storage project 335, Wheatland County Wind + storage |
80.0 MW | Paused / redesign |
| Solar project 915751, Granville County Solar |
80.0 MW | In study |
| Solar + storage project IC-971, Lowndes County Solar + storage |
80.0 MW | Paused / redesign |
| Solar + storage project IC-954, Conecuh County Solar + storage |
80.0 MW | Paused / redesign |
| Solar + storage project AG2-548, Jackson County Solar + storage · Hamden Energy LLC |
80.0 MW | In study |
| Halifax County Solar Solar |
80.0 MW | Agreement signed |
| Solar project AH1-665, Fleming County Solar · Hummingbird Energy LLC |
80.0 MW | In study |
| Solar + storage project AG2-665, Jackson County Solar + storage · Hamden Energy LLC |
80.0 MW | In study |
| Gas project IA-PNM-2020-05, San Juan County Gas · PNM ‚Äì Generation |
80.0 MW | Agreement signed |
| Solar + storage project 784, Natrona County Solar + storage · Dinosolar, LLC |
80.0 MW | Agreement signed |
| Backwater Solar Solar |
80.0 MW | Paused / redesign |
| Franklintown Farm Solar and BESS Solar + storage |
80.0 MW | Agreement signed |
| Battery storage project S0010, Iron County Battery storage · Enterprise Storage LLC |
80.0 MW | Agreement signed |
| Solar project 917443, Scotland County Solar |
80.0 MW | Agreement signed |
| Solar project J1209, Saline County Solar |
80.0 MW | Agreement signed |
| Solar + storage project IC-1053, Hale County Solar + storage |
80.0 MW | Paused / redesign |
| Battery storage project S0038, Converse County Battery storage |
80.0 MW | In study |
| Solar project AG2-659, Mecklenburg County Solar · Horizon Solar West, LLC |
80.0 MW | In study |
| Solar project IC-1224, Baldwin County Solar |
80.0 MW | Agreement signed |
| Battery storage project S0016, Sevier County Battery storage · Sigurd Storage Acquisitions, L.L.C. |
80.0 MW | Agreement signed |
| Solar project 569890, Wayne County Solar |
80.0 MW | Agreement signed |
| Swiftwater Solar Solar |
80.0 MW | Agreement signed |
| Solar project AH2-158, Somerset County Solar |
80.0 MW | In study |
| Big Star Storage Battery storage · RWE Solar Development, LLC |
80.0 MW | Agreement signed |
| Solar project Company IH, Pershing County Solar |
80.0 MW | Agreement signed |
| Other project PP00042, Granville County Other |
80.0 MW | In study |
| Currituck Solar Solar · Currituck Solar, LLC |
80.0 MW | Agreement signed |
| Pitt Solar Solar |
80.0 MW | Agreement signed |
| Solar + storage project IC-997, Baldwin County Solar + storage |
80.0 MW | Paused / redesign |
| Onshore wind project AE2-289, Allegany County Onshore wind |
80.0 MW | Agreement signed |
| Solar + storage project IC-1000, Baldwin County Solar + storage |
80.0 MW | Paused / redesign |
| Solar + storage project C2-210, Harney County Solar + storage |
80.0 MW | In study |
| Solar + storage project J4038, St. Francis County Solar + storage |
80.0 MW | In study |
| Solar + storage project GEN-2024-361, Lincoln County Solar + storage |
80.0 MW | In study |
| Solar + storage project IC-1087, Russell County Solar + storage |
80.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)