🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Carolina

SOLAR · SOUTHEAST

Solar project 564510, Bladen County

Solar project 564510, Bladen County is a 80.0 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Bladen County, North Carolina, connecting to Duke Energy Progress.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
564510
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
CUMBERLAND - DELCO 230KV
Location
Bladen County, North Carolina
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Other
Study phase
Engineering Design - In Progress
Queue status
Active
Entered queue
22 June 2022
Proposed online date
January 2027

Location

Marker shows the centre of Bladen County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Bladen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem