πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

SOLAR Β· SOUTHEAST

Solar project 169716, Bladen County

Solar project 169716, Bladen County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Bladen County, North Carolina, connecting to Duke Energy Progress.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
169716
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
Cumberland - Delco 230 kV
Location
Bladen County, North Carolina
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Other
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 May 2021

Location

Marker shows the centre of Bladen County; the queue data does not give exact sites.

Power plants in North Carolina Β· Transmission lines in North Carolina

Other requests in Bladen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem