Solar + storage project 784, Natrona County is a 80.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Natrona County, Wyoming, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Aug 2016 (completed)
  2. ConsentedMay 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
784
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Dinosolar, LLC
Connection point (POI)
Casper substation
Location
Natrona County, Wyoming
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
IA executed 5/22/19
Queue status
Active
Entered queue
4 August 2016
Agreement signed
22 May 2019
Proposed online date
December 2024

Location

Marker shows the centre of Natrona County; the queue data does not give exact sites.