United States › Grid › Interconnection queues › Wyoming

ONSHORE WIND · WEST

Onshore wind project 171, Natrona County

Onshore wind project 171, Natrona County is a 16.5 MW onshore wind request built and operating in the West interconnection queue, in Natrona County, Wyoming, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Nov 2007 (completed)
  2. ConsentedApr 2009 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
171
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Chevron Global Generation
Connection point (POI)
Sand Hills Line between Casper & Platte Junction
Location
Natrona County, Wyoming
Technology
Wind: 16.5 MW
Total requested
16.5 MW
Service type
Network resource (NRIS)
Study phase
IA signed April 29, 2009
Queue status
Operational
Entered queue
8 November 2007
Agreement signed
29 April 2009
Proposed online date
December 2009

Location

Marker shows the centre of Natrona County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Natrona County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem