🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wyoming

SOLAR + STORAGE · WEST

Solar + storage project 783, Natrona County

Solar + storage project 783, Natrona County is a 30.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Natrona County, Wyoming, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Aug 2016 (completed)
  2. ConsentedFeb 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
783
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Dinosolar, LLC
Connection point (POI)
Bar Nunn substation
Location
Natrona County, Wyoming
Technology
Solar: 30.0 MW · Battery
Total requested
30.0 MW
Service type
Energy only (ERIS)
Study phase
IA executed 2/12/20, combined with Q0801 and Q0802
Queue status
Active
Entered queue
3 August 2016
Agreement signed
12 February 2020
Proposed online date
December 2024

Location

Marker shows the centre of Natrona County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Natrona County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem