United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMPitt Solar
Pitt Solar is a 80.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Pitt County, North Carolina, connecting to Dominion.
Queue statusConsented
- PlanningQueued Oct 2016 (completed)
- ConsentedFeb 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AC1-189
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Chinquapin-Everetts 230kV
- Location
- Pitt County, North Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 31 October 2016
- Agreement signed
- 1 February 2022
- Proposed online date
- November 2026
Location
Marker shows the centre of Pitt County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Pitt County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem