Big Star Storage

Big Star Storage is a 80.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bastrop County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedOct 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0469
Grid region
ERCOT (Texas)
Developer
RWE Solar Development, LLC
Connection point (POI)
Tap 345kV 9074 Lytton - 9073 Holman
Location
Bastrop County, Texas
Technology
Battery: 80.0 MW
Total requested
80.0 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 January 2020
Agreement signed
2 October 2020
Proposed online date
January 2026

Location

Marker shows the centre of Bastrop County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bastrop County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem