United States › Grid › Interconnection queues › Texas
GAS · ERCOTFort Worth Power Core Bastrop Gas Plant
Fort Worth Power Core Bastrop Gas Plant is a 506 MW gas request in interconnection study in the ERCOT interconnection queue, in Bastrop County, Texas.
Queue statusIn planning
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0560
- Grid region
- ERCOT (Texas)
- Developer
- Fort Worth Power Core LLC
- Connection point (POI)
- Tap 345kV 7042 ZORN - 7040 AUSTROP
- Location
- Bastrop County, Texas
- Technology
- Gas: 506 MW
- Total requested
- 506 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 27 May 2025
- Proposed online date
- September 2029
Location
Marker shows the centre of Bastrop County; the queue data does not give exact sites.
Other requests in Bastrop County
- Bastrop Peaking Generators (TEF-Due Diligence)Gas · 1,104 MW · agreement signed
- Big Star SolarSolar · 203 MW · agreement signed
- Waterloo Solar 1Solar + storage · 201 MW · agreement signed
- Waterloo BESS 1Solar + storage · 106 MW · agreement signed
- Big Star StorageBattery storage · 80.0 MW · agreement signed
- Sim Gideon Combined CycleGas · 880 MW · in study
- Lost Pines Power ParkGas · 880 MW · in study
- Lund Storage Center 1Battery storage · 408 MW · in study
- Sim Gideon Gas RiceGas · 226 MW · in study
- Techne BESSBattery storage · 203 MW · in study
- Antonio Road BESSBattery storage · 156 MW · in study
- Lost Pines Gas Recip Phase 2Gas · 113 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem