United States › Grid › Interconnection queues › Maryland
ONSHORE WIND · PJMOnshore wind project AE2-289, Allegany County
Onshore wind project AE2-289, Allegany County is a 80.0 MW onshore wind request with a signed interconnection agreement in the PJM interconnection queue, in Allegany County, Maryland, connecting to APS.
Queue statusConsented
- PlanningQueued Mar 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2021 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AE2-289
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Frostburg 138 kV
- Location
- Allegany County, Maryland
- Technology
- Wind: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 29 March 2019
- Proposed online date
- December 2021
Location
Marker shows the centre of Allegany County; the queue data does not give exact sites.
Other requests in Allegany County
- Solar project AH2-052, Allegany CountySolar · 2.0 MW · in study
- Dans MountainOnshore wind · 54.9 MW · built
- Jade MeadowSolar · 19.8 MW · built
- Solar project AF2-360, Allegany CountySolar · 125 MW · withdrawn
- Solar project AH1-621, Allegany CountySolar · 120 MW · withdrawn
- Solar project AG2-615, Allegany CountySolar · 100 MW · withdrawn
- Battery storage project AG2-308, Allegany CountyBattery storage · 100 MW · withdrawn
- Other project AE1-077, Allegany CountyOther · 100 MW · withdrawn
- Solar + storage project AH1-342, Allegany CountySolar + storage · 75.0 MW · withdrawn
- Solar project AF1-044, Allegany CountySolar · 45.0 MW · withdrawn
- Pigtoe Bobcat SolarSolar · 20.0 MW · withdrawn
- Dan's Mountain Solar ProjectSolar · 19.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem