ONSHORE WIND · PJM

Onshore wind project AE2-289, Allegany County

Onshore wind project AE2-289, Allegany County is a 80.0 MW onshore wind request with a signed interconnection agreement in the PJM interconnection queue, in Allegany County, Maryland, connecting to APS.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-289
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Frostburg 138 kV
Location
Allegany County, Maryland
Technology
Wind: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
29 March 2019
Proposed online date
December 2021

Location

Marker shows the centre of Allegany County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland