United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR + STORAGE Β· PJM

Solar + storage project AH1-342, Allegany County

Solar + storage project AH1-342, Allegany County is a 75.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Allegany County, Maryland, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-342
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Carlos Junction 138 kV II
Location
Allegany County, Maryland
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
July 2025
Withdrawn
October 2021

Location

Marker shows the centre of Allegany County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Allegany County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem