United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR Β· PJM

Solar project AF1-044, Allegany County

Solar project AF1-044, Allegany County is a 45.0 MW solar request withdrawn in the PJM interconnection queue, in Allegany County, Maryland, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2019 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-044
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Wye Mills-Longwood 69 kV
Location
Allegany County, Maryland
Technology
Solar: 45.0 MW
Total requested
45.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
28 June 2019
Proposed online date
November 2021
Withdrawn
February 2020

Location

Marker shows the centre of Allegany County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Allegany County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem