United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMHalifax County Solar
Halifax County Solar is a 80.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Halifax County, North Carolina, connecting to Dominion.
Queue statusConsented
- PlanningQueued Nov 2016 (completed)
- ConsentedJul 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AC1-208
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Cox-Whitakers 115kV
- Location
- Halifax County, North Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 1 November 2016
- Agreement signed
- 22 July 2020
- Proposed online date
- August 2026
Location
Marker shows the centre of Halifax County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Halifax County
- Sweetleaf SolarSolar · 60.0 MW · suspended
- Sweetleaf SolarSolar · 33.0 MW · suspended
- Chestnut SolarSolar · 66.0 MW · built
- American Beech SolarSolar · 60.0 MW · built
- Chestnut SolarSolar · 8.9 MW · built
- Solar + storage project AD1-029, Halifax CountySolar + storage · 110 MW · withdrawn
- Solar + storage project AI1-113, Halifax CountySolar + storage · 74.9 MW · withdrawn
- Solar project AF2-219, Halifax CountySolar · 58.0 MW · withdrawn
- Solar project AA2-056, Halifax CountySolar · 20.0 MW · withdrawn
- Solar project AC2-083, Halifax CountySolar · 20.0 MW · withdrawn
- Solar project AA2-055, Halifax CountySolar · 20.0 MW · withdrawn
- N301 SolarSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem