SOLAR · PJMChestnut Solar
Chestnut Solar is a 8.9 MW solar request built and operating in the PJM interconnection queue, in Halifax County, North Carolina, connecting to Dominion.
Request details
- Queue ID
- AA2-165
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Hornertown-Whitakers 115kV
- Location
- Halifax County, North Carolina
- Technology
- Solar: 8.9 MW
- Total requested
- 8.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 30 April 2015
- Proposed online date
- December 2019
- Came online
- November 2019
Location
Marker shows the centre of Halifax County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Halifax County
- Halifax County SolarSolar · 80.0 MW · agreement signed
- Sweetleaf SolarSolar · 60.0 MW · suspended
- Sweetleaf SolarSolar · 33.0 MW · suspended
- Chestnut SolarSolar · 66.0 MW · built
- American Beech SolarSolar · 60.0 MW · built
- Solar + storage project AD1-029, Halifax CountySolar + storage · 110 MW · withdrawn
- Solar + storage project AI1-113, Halifax CountySolar + storage · 74.9 MW · withdrawn
- Solar project AF2-219, Halifax CountySolar · 58.0 MW · withdrawn
- Solar project AA2-056, Halifax CountySolar · 20.0 MW · withdrawn
- Solar project AC2-083, Halifax CountySolar · 20.0 MW · withdrawn
- Solar project AA2-055, Halifax CountySolar · 20.0 MW · withdrawn
- N301 SolarSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem