United States › Grid › Interconnection queues › Alabama
SOLAR + STORAGE · SOUTHEASTSolar + storage project IC-971, Lowndes County
Solar + storage project IC-971, Lowndes County is a 80.0 MW solar + storage request suspended in the Southeast interconnection queue, in Lowndes County, Alabama, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued Jul 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-971
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Greenville - Pintlala 115 kV Line
- Location
- Lowndes County, Alabama
- Technology
- Solar: 80.0 MW · Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Suspended
- Entered queue
- 8 July 2021
- Proposed online date
- June 2026
Location
Marker shows the centre of Lowndes County; the queue data does not give exact sites.
Other requests in Lowndes County
- Solar + storage project IC-955, Lowndes CountySolar + storage · 58.0 MW · suspended
- Coal project IC-100, Lowndes CountyCoal · 800 MW · withdrawn
- Coal project IC-103, Lowndes CountyCoal · 800 MW · withdrawn
- Solar project IC-968, Lowndes CountySolar · 300 MW · withdrawn
- Solar + storage project IC-1169, Lowndes CountySolar + storage · 200 MW · withdrawn
- Solar project IC-317, Lowndes CountySolar · 150 MW · withdrawn
- Solar + storage project IC-1182, Lowndes CountySolar + storage · 138 MW · withdrawn
- Solar project IC-1208, Lowndes CountySolar · 120 MW · withdrawn
- Gas project IC-388, Lowndes CountyGas · 100 MW · withdrawn
- Solar project 25-IC-AM, Lowndes CountySolar · 100 MW · withdrawn
- Solar + storage project IC-1093, Lowndes CountySolar + storage · 80.0 MW · withdrawn
- Solar + storage project IC-1020, Lowndes CountySolar + storage · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem