GAS Β· SOUTHEAST

Gas project IC-388, Lowndes County

Gas project IC-388, Lowndes County is a 100 MW gas request withdrawn in the Southeast interconnection queue, in Lowndes County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2014 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-388
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Burkville - Hunter 115 kV Line
Location
Lowndes County, Alabama
Technology
Gas: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
30 June 2014
Withdrawn
June 2017

Location

Marker shows the centre of Lowndes County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Lowndes County