🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Walker Solar Two

Walker Solar Two is a 80.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Juniata County, Pennsylvania, connecting to PPL.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-361
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Mifflintown Tap 69 kV
Location
Juniata County, Pennsylvania
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 March 2020
Proposed online date
September 2026

Location

Marker shows the centre of Juniata County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Juniata County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem