Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 89 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Surplus; J291
Solar
169 MWIn study Scott, ILMISO Aug 2025target 2028
Buffalo Gap 3 Wind Repower
Onshore wind · Buffalo Gap Wind Farm 3, LLC
169 MWAgreement signed Taylor, TXERCOT Dec 2024target 2026
Donna Solar
Solar + storage · Donna Solar LLC
168 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Battery Storage
Battery storage
168 MWIn study Bristol, MAISO-NE Jun 2023target 2027
Carol Battery
Battery storage
168 MWPaused / redesign Potter, TXERCOT Jun 2019
Jalisco Cogen
Gas · HEP Power Generation, LLC
168 MWIn study Nueces, TXERCOT Aug 2024target 2029
Bell Song Solar 2
Solar · Bell Song Solar, LLC 2
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar 3
Solar · Bell Song Solar, LLC_3
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar
Solar · Bell Song Solar, LLC
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2029
Courthouse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
167 MWIn study Charlotte, VAPJM Mar 2020target 2031
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Gas project 758, Elmore County
Gas
167 MWIn study Elmore, IDWest Mar 2025target 2028
Battery storage project GEN-2024-084, Lawrence County
Battery storage
167 MWIn study Lawrence, MOSPP Oct 2024target 2028
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Onshore wind project GI-TC-2024-11, Kit Carson County
Onshore wind
167 MWAgreement signed Kit Carson, COWest May 2024target 2027
Fagus Solar Park 2 SLF
Solar + storage · Excel Advantage Services, LLC dba Misae Solar Park II
167 MWAgreement signed Childress, TXERCOT Jun 2024target 2026
Fagus Solar Park 1 SLF
Solar + storage · Excel Advantage Services, LLC dba Misae Solar Park II
166 MWAgreement signed Childress, TXERCOT May 2018target 2026
Lone Star Industrial Park Gas Power Project
Gas · LONE STAR INDUSTRIAL PARK, LLC
166 MWIn study Morris, TXERCOT Sep 2024target 2028
Solar + storage project C2-99, Emery County
Solar + storage
166 MWIn study Emery, UTWest May 2022target 2026
Onshore wind project GEN-2011-020, Ellis County
Onshore wind
166 MWAgreement signed Ellis, OKSPP Mar 2011target 2027
CAROL wind
Onshore wind
165 MWPaused / redesign Potter, TXERCOT Dec 2018target 2024
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028
Wind + storage project J3962, Bay County
Wind + storage
165 MWIn study Bay, MIMISO Mar 2025target 2030
Solar project J1174, Worth County
Solar
165 MWUnder construction Worth, IAMISO Mar 2018target 2024
Solar project 25-IC-1355, Jasper County
Solar
165 MWIn study Jasper, MSSoutheast Apr 2025target 2029
Onshore wind project J1175, Worth County
Onshore wind
165 MWAgreement signed Worth, IAMISO Mar 2018target 2024
Solar project J1669, Jefferson Davis Parish County
Solar
165 MWIn study Jefferson Davis Parish, LAMISO Jun 2020target 2025
Hart Wind (Old POI)
Onshore wind
165 MWPaused / redesign Castro, TXERCOT Feb 2014
Solar project J2873, Simpson County
Solar
165 MWIn study Simpson, MSMISO Sep 2022target 2027
Battery storage project Q479, Maricopa County
Battery storage
165 MWIn study Maricopa, AZWest Sep 2022target 2028
Solar project J3987, Amite County
Solar
165 MWIn study Amite, MSMISO Oct 2024target 2030
Solar project J1917, Livingston County
Solar
165 MWIn study Livingston, MIMISO Aug 2021target 2023
Solar project J1442, Polk County
Solar
165 MWUnder construction Polk, TXMISO Apr 2019target 2025
Solar + storage project GI-CS-2025-12, Las Animas County
Solar + storage
165 MWIn study Las Animas, COWest Sep 2025target 2029
Solar + storage project 25-IC-1339, Hancock County
Solar + storage
165 MWIn study Hancock, GASoutheast Apr 2025target 2029
Lockhart Solar 2
Solar + storage
165 MWAgreement signed San Bernardino, CACAISO Apr 2019target 2026
Houston IV BESS
Battery storage · SMT Houston IV LLC
165 MWAgreement signed Harris, TXERCOT Jul 2023target 2026
Solar
Solar
165 MWAgreement signed Somerset, MEISO-NE Feb 2021target 2029
Dos Rios Energy Storage SLF
Battery storage · DOS RIOS SOLAR, LLC
165 MWAgreement signed Milam, TXERCOT Nov 2022target 2027
Onshore wind project J2576, Louisa County
Onshore wind
164 MWIn study Louisa, IAMISO Sep 2022target 2025
Solar project AI1-148, Kankakee County
Solar
164 MWIn study Kankakee, ILPJM Sep 2022target 2026
Zeppelin Energy Storage
Battery storage · ZEPPELIN ENERGY STORAGE LLC
164 MWIn study Tom Green, TXERCOT Jan 2023target 2028
Dove Creek Solar
Solar + storage · Dove Creek Solar, LLC
164 MWIn study Tom Green, TXERCOT Jul 2024target 2028
Janus
Solar + storage
164 MWAgreement signed Colusa, CACAISO Apr 2018target 2026
BRP Pollux BESS
Battery storage · BRP Pollux BESS LLC
163 MWIn study Bosque, TXERCOT Jan 2022target 2026
Onshore wind project J3900, Sunflower County
Onshore wind
163 MWIn study Sunflower, MSMISO Dec 2024target 2030
Dove Creek Storage
Solar + storage · Dove Creek Solar, LLC
163 MWIn study Tom Green, TXERCOT Jul 2024target 2028
Concho Pearl Storage
Solar + storage · Concho Pearl Solar, LLC
162 MWAgreement signed Concho, TXERCOT Dec 2022target 2027
Lupinus Solar 1
Solar + storage · Lupinus Solar, LLC
162 MWAgreement signed Franklin, TXERCOT Dec 2021target 2027
Page 89 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)