United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J2873, Simpson County
Solar project J2873, Simpson County is a 165 MW solar request in interconnection study in the MISO interconnection queue, in Simpson County, Mississippi, connecting to COOPERATIVE ENERGY.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2873
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- COOPERATIVE ENERGY
- Connection point (POI)
- Magee 161 - White Oak 161.0kV
- Location
- Simpson County, Mississippi
- Technology
- Solar: 165 MW
- Total requested
- 165 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- October 2027
Location
Marker shows the centre of Simpson County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Simpson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem