United States › Grid › Interconnection queues › Illinois
SOLAR · MISOSurplus; J291
Surplus; J291 is a 169 MW solar request in interconnection study in the MISO interconnection queue, in Scott County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1114
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Alsey Generation Station
- Location
- Scott County, Illinois
- Technology
- Solar: 169 MW
- Total requested
- 169 MW
- Queue status
- Active
- Entered queue
- 19 August 2025
- Proposed online date
- September 2028
Location
Marker shows the centre of Scott County; the queue data does not give exact sites.
Other requests in Scott County
- Solar project J4000, Scott CountySolar · 343 MW · in study
- Solar project J4031, Scott CountySolar · 245 MW · in study
- Solar project J3949, Scott CountySolar · 245 MW · in study
- Gas project J291, Scott CountyGas · 45.0 MW · built
- Solar project J2703, Scott CountySolar · 398 MW · withdrawn
- Solar project J3174, Scott CountySolar · 180 MW · withdrawn
- Solar project J1012, Scott CountySolar · 100 MW · withdrawn
- Solar project J3683, Scott CountySolar · 100 MW · withdrawn
- Solar project J3396, Scott CountySolar · 30.0 MW · withdrawn
- Solar project J3392, Scott CountySolar · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem