United States › Grid › Interconnection queues › Illinois
SOLAR · MISOSolar project J3949, Scott County
Solar project J3949, Scott County is a 245 MW solar request in interconnection study in the MISO interconnection queue, in Scott County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3949
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN TRANSMISSION COMPANY OF ILLINOIS
- Connection point (POI)
- 7MEREDOSIA - 7TURNER 345.0kV
- Location
- Scott County, Illinois
- Technology
- Solar: 245 MW
- Total requested
- 245 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 April 2025
- Proposed online date
- January 2030
Location
Marker shows the centre of Scott County; the queue data does not give exact sites.
Other requests in Scott County
- Solar project J4000, Scott CountySolar · 343 MW · in study
- Solar project J4031, Scott CountySolar · 245 MW · in study
- Surplus; J291Solar · 169 MW · in study
- Gas project J291, Scott CountyGas · 45.0 MW · built
- Solar project J2703, Scott CountySolar · 398 MW · withdrawn
- Solar project J3174, Scott CountySolar · 180 MW · withdrawn
- Solar project J1012, Scott CountySolar · 100 MW · withdrawn
- Solar project J3683, Scott CountySolar · 100 MW · withdrawn
- Solar project J3396, Scott CountySolar · 30.0 MW · withdrawn
- Solar project J3392, Scott CountySolar · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem