ONSHORE WIND · ERCOTBuffalo Gap 3 Wind Repower
Buffalo Gap 3 Wind Repower is a 169 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Taylor County, Texas.
Queue statusConsented
- PlanningQueued Dec 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0626
- Grid region
- ERCOT (Texas)
- Developer
- Buffalo Gap Wind Farm 3, LLC
- Connection point (POI)
- 6216 Bluff_Creek 138kV
- Location
- Taylor County, Texas
- Technology
- Wind: 169 MW
- Total requested
- 169 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 3 December 2024
- Proposed online date
- December 2026
Location
Marker shows the centre of Taylor County; the queue data does not give exact sites.
Other requests in Taylor County
- Horse13 CallD repowerOnshore wind · 44.0 MW · agreement signed
- HHGT repower Horse13+CallDOnshore wind · 44.0 MW · agreement signed
- Abilene Elmcreek BESSBattery storage · 9.9 MW · agreement signed
- Abilene Industrial Park BESSBattery storage · 9.9 MW · agreement signed
- Dog Star Solar IISolar · 503 MW · in study
- Dog Star Solar ISolar · 503 MW · in study
- Forts Trail BESSSolar + storage · 209 MW · in study
- Forts Trail BESS 2Solar + storage · 206 MW · in study
- Taylor County Paul StorageBattery storage · 205 MW · in study
- Forts Trail SolarSolar + storage · 201 MW · in study
- Chimney Rock BESSBattery storage · 156 MW · in study
- Summerhill BESSBattery storage · 143 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem