🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Taylor County Paul Storage

Taylor County Paul Storage is a 205 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Taylor County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0618
Grid region
ERCOT (Texas)
Developer
DM-TCP, LLC
Connection point (POI)
6260 Abilene South Substation 138kV
Location
Taylor County, Texas
Technology
Battery: 205 MW
Total requested
205 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 December 2024
Proposed online date
June 2028

Location

Marker shows the centre of Taylor County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Taylor County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem