Solar + storage project 25-IC-1339, Hancock County

Solar + storage project 25-IC-1339, Hancock County is a 165 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Hancock County, Georgia, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-IC-1339
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Branch - Springhill Church 230 kV Line
Location
Hancock County, Georgia
Technology
Solar: 165 MW · Battery
Total requested
165 MW
Service type
Energy only (ERIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
14 April 2025
Proposed online date
March 2029

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Hancock County