SOLAR Β· SOUTHEAST

Solar project IC-586, Hancock County

Solar project IC-586, Hancock County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Hancock County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2017 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-586
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Branch - Warrenton Primary 230 KV Line
Location
Hancock County, Georgia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
27 January 2017
Withdrawn
March 2019

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.