🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR + STORAGE · WEST

Solar + storage project GI-CS-2025-12, Las Animas County

Solar + storage project GI-CS-2025-12, Las Animas County is a 165 MW solar + storage request in interconnection study in the West interconnection queue, in Las Animas County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-CS-2025-12
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Walsenburg - Gladstone 230kV Line
Location
Las Animas County, Colorado
Technology
Solar: 165 MW · Battery
Total requested
165 MW
Service type
NRIS and ERIS
Study phase
Cluster Study
Queue status
Active
Entered queue
24 September 2025
Proposed online date
December 2029

Location

Marker shows the centre of Las Animas County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Las Animas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem