🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project GI-TC-2021-04, Las Animas County

Solar project GI-TC-2021-04, Las Animas County is a 40.0 MW solar request built and operating in the West interconnection queue, in Las Animas County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusOperating
  1. PlanningQueued Mar 2021 (completed)
  2. ConsentedSep 2024 (completed)
  3. Construction (completed)
  4. OperatingSep 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-TC-2021-04
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Valent 230kV Switching Station
Location
Las Animas County, Colorado
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
15 March 2021
Agreement signed
1 September 2024
Proposed online date
September 2024
Came online
September 2024

Location

Marker shows the centre of Las Animas County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Las Animas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem