United States βΊ Grid βΊ Interconnection queues βΊ Colorado
ONSHORE WIND Β· WESTOnshore wind project GI-2008-22, Las Animas County
Onshore wind project GI-2008-22, Las Animas County is a 500 MW onshore wind request withdrawn in the West interconnection queue, in Las Animas County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2008 (completed)
- Withdrawn / abandonedSep 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2008-22
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Boone Substation
- Location
- Las Animas County, Colorado
- Technology
- Wind: 500 MW
- Total requested
- 500 MW
- Service type
- NRIS and ERIS
- Study phase
- Feasibility Study underway Request Withdrawn 09/30/13
- Queue status
- Withdrawn
- Entered queue
- 14 October 2008
- Proposed online date
- June 2010
- Withdrawn
- September 2013
Location
Marker shows the centre of Las Animas County; the queue data does not give exact sites.
Other requests in Las Animas County
- Solar + storage project GI-CS-2025-12, Las Animas CountySolar + storage Β· 165 MW Β· in study
- Solar + storage project GI-CS-2025-23, Las Animas CountySolar + storage Β· 150 MW Β· in study
- Solar + storage project GI-DISIS-2021-11, Las Animas CountySolar + storage Β· 300 MW Β· suspended
- Solar project TI-18-0809, Las Animas CountySolar Β· 100 MW Β· built
- Solar project GI-TC-2021-04, Las Animas CountySolar Β· 40.0 MW Β· built
- Solar project TI-15-0612, Las Animas CountySolar Β· 30.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem