🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project TI-15-0612, Las Animas County

Solar project TI-15-0612, Las Animas County is a 30.0 MW solar request built and operating in the West interconnection queue, in Las Animas County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusOperating
  1. PlanningQueued Jun 2015 (completed)
  2. ConsentedSep 2016 (completed)
  3. Construction (completed)
  4. OperatingSep 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
TI-15-0612
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Tyrone 115kV Tap
Location
Las Animas County, Colorado
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
17 June 2015
Agreement signed
15 September 2016
Proposed online date
September 2016
Came online
September 2016

Location

Marker shows the centre of Las Animas County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Las Animas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem