United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· ERCOTCarol Battery
Carol Battery is a 168 MW battery storage request suspended in the ERCOT interconnection queue, in Potter County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jun 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 21INR0363
- Grid region
- ERCOT (Texas)
- Location
- Potter County, Texas
- Technology
- Battery: 168 MW
- Total requested
- 168 MW
- Queue status
- Suspended
- Entered queue
- 17 June 2019
Location
Marker shows the centre of Potter County; the queue data does not give exact sites.
Other requests in Potter County
- Solar + storage project GEN-2024-266, Potter CountySolar + storage Β· 500 MW Β· in study
- Battery storage project ERAS-2025-036, Potter CountyBattery storage Β· 140 MW Β· in study
- Carol SolarSolar Β· 223 MW Β· suspended
- CAROL windOnshore wind Β· 165 MW Β· suspended
- Solar project GEN-2023-239, Potter CountySolar Β· 300 MW Β· withdrawn
- Solar project GEN-2023-238, Potter CountySolar Β· 280 MW Β· withdrawn
- Battery storage project GEN-2022-133, Potter CountyBattery storage Β· 250 MW Β· withdrawn
- Battery storage project GEN-2023-208, Potter CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project GEN-2019-036, Potter CountySolar Β· 70.0 MW Β· withdrawn
- Battery storage project GEN-2019-038, Potter CountyBattery storage Β· 50.0 MW Β· withdrawn
- Solar project GEN-2017-107, Potter CountySolar Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem