SOLAR Β· SPP

Solar project GEN-2019-036, Potter County

Solar project GEN-2019-036, Potter County is a 70.0 MW solar request withdrawn in the SPP interconnection queue, in Potter County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedMay 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2019-036
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Potter County 230kV
Location
Potter County, Texas
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
15 May 2019
Proposed online date
June 2021
Withdrawn
May 2022

Location

Marker shows the centre of Potter County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Potter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem