πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· SPP

Battery storage project GEN-2019-038, Potter County

Battery storage project GEN-2019-038, Potter County is a 50.0 MW battery storage request withdrawn in the SPP interconnection queue, in Potter County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedMay 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2019-038
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Potter County 230kV
Location
Potter County, Texas
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 May 2019
Proposed online date
June 2021
Withdrawn
May 2022

Location

Marker shows the centre of Potter County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Potter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem