ONSHORE WIND · SPP

Onshore wind project GEN-2011-020, Ellis County

Onshore wind project GEN-2011-020, Ellis County is a 166 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Ellis County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Mar 2011 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2011-020
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Woodward EHV 345kV
Location
Ellis County, Oklahoma
Technology
Wind: 166 MW
Total requested
166 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
31 March 2011
Proposed online date
October 2027

Location

Marker shows the centre of Ellis County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Ellis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem