ONSHORE WIND Β· SPP

Onshore wind project GEN-2005-006, Ellis County

Onshore wind project GEN-2005-006, Ellis County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Ellis County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2005 (completed)
  2. Withdrawn / abandonedMar 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2005-006
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Location
Ellis County, Oklahoma
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
22 March 2005
Proposed online date
December 2006
Withdrawn
March 2006

Location

Marker shows the centre of Ellis County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Ellis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem