United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2012-025, Ellis County

Onshore wind project GEN-2012-025, Ellis County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Ellis County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2012 (completed)
  2. Withdrawn / abandonedOct 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2012-025
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
TAP HITCHLAND-WOODWARD 345KV
Location
Ellis County, Oklahoma
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 September 2012
Proposed online date
December 2014
Withdrawn
October 2012

Location

Marker shows the centre of Ellis County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma