Solar project J1174, Worth County

Solar project J1174, Worth County is a 165 MW solar request under construction in the MISO interconnection queue, in Worth County, Iowa, connecting to ITC MIDWEST.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedFeb 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1174
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Ledyard - Colby 345 kV Line Tap
Location
Worth County, Iowa
Technology
Solar: 165 MW
Total requested
165 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
7 February 2022
Proposed online date
June 2024

Location

Marker shows the centre of Worth County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Worth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem