🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project G046, Worth County

Onshore wind project G046, Worth County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Worth County, Iowa.

Queue statusOperating
  1. PlanningQueued Jul 2000 (completed)
  2. ConsentedNov 2003 (completed)
  3. Construction (completed)
  4. OperatingJan 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G046
Grid region
MISO (Midcontinent)
Connection point (POI)
Worth County switching station
Location
Worth County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
23 July 2000
Agreement signed
24 November 2003
Proposed online date
January 2002
Came online
January 2002

Location

Marker shows the centre of Worth County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Worth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem