United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 166
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 956971, Rowan County Gas |
28.0 MW | In study |
| Other project GI-2021-144, Imperial County Other |
28.0 MW | In study |
| Onshore wind project C2-14, Carbon County Onshore wind · PacifiCorp |
28.0 MW | Agreement signed |
| Gas project 956974, Rockingham County Gas |
28.0 MW | In study |
| Onshore wind project PIS053, Carbon County Onshore wind · PacifiCorp |
28.0 MW | In study |
| Solar project AI2-424, Huntington County Solar |
28.0 MW | In study |
| Hillboro Wind Wind + storage · Abei Energy Green XI LLC |
27.8 MW | In study |
| Other project GEN-2024-GR4, Cherokee County Other |
27.1 MW | Agreement signed |
| Gas project IC-1012, Autauga County Gas |
27.0 MW | In study |
| Gas project G0620, Umatilla County Gas |
27.0 MW | In study |
| Hydro project E291 Hydro |
27.0 MW | Agreement signed |
| Hydro project 323, Marion County Hydro |
27.0 MW | Agreement signed |
| Hydro project 322, Marion County Hydro |
27.0 MW | Agreement signed |
| Zeus Rusk Solar Solar + storage · Rusk Solar, LLC |
26.8 MW | In study |
| Solar project AI2-339, Nicholas County Solar |
26.8 MW | In study |
| Solar project AI2-427, Licking County Solar |
26.4 MW | In study |
| Fowler Ranch Storage Battery storage · Crane BESS, LLC |
26.1 MW | In study |
| Solar project 957449, Greenwood County Solar |
26.1 MW | In study |
| Onshore wind project C2-11, Carbon County Onshore wind · PacifiCorp |
26.0 MW | Agreement signed |
| 360 Solar Center, LLC Solar · 360 Solar Center, LLC |
26.0 MW | In study |
| Hydro project Q63, Kootenai County Hydro |
26.0 MW | Agreement signed |
| 360 Solar Center, LLC Solar · 360 Solar Center, LLC |
26.0 MW | In study |
| Gas project PP00012, Wayne County Gas |
26.0 MW | Agreement signed |
| Gas project 904269, Wayne County Gas · Duke Energy Progress, LLC |
26.0 MW | Agreement signed |
| Blue Creek Wind Farm Solar |
26.0 MW | Paused / redesign |
| Onshore wind project PIS050, Carbon County Onshore wind · PacifiCorp |
26.0 MW | In study |
| Hydro project 63, Kootenai County Hydro |
26.0 MW | Agreement signed |
| Gas project GI-116, New Madrid County Gas |
26.0 MW | Agreement signed |
| Solar project AH2-263, Marion County Solar |
25.8 MW | In study |
| NET Power Demonstration plant Gas · NET Power LLC |
25.5 MW | In study |
| Kennedy Storage Solar + storage · Kennedy Bypass Solar LLC |
25.3 MW | In study |
| Burro Loco Energy Storage Battery storage · VESI |
25.1 MW | In study |
| Gas project J1798, Wayne County Gas |
25.0 MW | Agreement signed |
| Battery storage project J1323, Lagrange County Battery storage |
25.0 MW | Agreement signed |
| Decatur Battery Storage Battery storage · Decatur Storage LLC |
25.0 MW | Agreement signed |
| Solar project AH1-570 Solar · South Fork Solar, LLC |
25.0 MW | In study |
| Solar project 957084, Darlington County Solar |
25.0 MW | In study |
| Solar project AH2-266, Charles County Solar |
25.0 MW | In study |
| Solar project T2-079, Jefferson County Solar |
25.0 MW | In study |
| Fluorite Solar Solar |
25.0 MW | Paused / redesign |
| Surplus; J1188 Other |
25.0 MW | In study |
| Other project PP00053, Darlington County Other |
25.0 MW | In study |
| Battery storage project AH2-244, Allegheny County Battery storage |
25.0 MW | In study |
| Battery storage project J1602, Ouachita Parish County Battery storage |
25.0 MW | Agreement signed |
| Surplus; J1000 Other |
25.0 MW | In study |
| Onshore wind project G0827, Sherman County Onshore wind |
25.0 MW | In study |
| Surplus; J1305 Other |
25.0 MW | In study |
| Onshore wind project GEN-2019-001, Pratt County Onshore wind |
25.0 MW | Agreement signed |
| Gas project 25-IC-1316, Kemper County Gas |
25.0 MW | In study |
| Amelia Energy Facility Solar · Amelia Energy Facility, LLC |
25.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)