HYDRO Β· MISOHydro project E291
Hydro project E291 is a 27.0 MW hydro request with a signed interconnection agreement in the MISO interconnection queue.
Queue statusConsented
- PlanningQueued May 2012 (completed)
- ConsentedOct 2013 (current stage)
- Construction (not yet reached)
- OperatingJul 2020 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- E291
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Rich 138 kV substation
- Location
- Texas
- Technology
- Hydro: 27.0 MW
- Total requested
- 27.0 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 15 May 2012
- Agreement signed
- 22 October 2013
- Proposed online date
- January 2016
- Came online
- July 2020
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem