United States › Grid › Interconnection queues › Idaho
HYDRO · WESTHydro project Q63, Kootenai County
Hydro project Q63, Kootenai County is a 26.0 MW hydro request with a signed interconnection agreement in the West interconnection queue, in Kootenai County, Idaho, connecting to Avista Utilities.
Queue statusConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- Q63
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- Post Falls 115kV Station
- Location
- Kootenai County, Idaho
- Technology
- Hydro: 26.0 MW
- Total requested
- 26.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA
- Queue status
- Active
- Proposed online date
- March 2028
Location
Marker shows the centre of Kootenai County; the queue data does not give exact sites.
Other requests in Kootenai County
- Hydro project 63, Kootenai CountyHydro · 26.0 MW · agreement signed
- Gas project CS25-05, Kootenai CountyGas · 102 MW · in study
- Gas project CS25-04, Kootenai CountyGas · 102 MW · in study
- Battery storage project C2-19, Kootenai CountyBattery storage · 1,800 MW · withdrawn
- Kootenai GenerationGas · 1,300 MW · withdrawn
- 500MW Taft-BellGas · 500 MW · withdrawn
- Gas project CS24-05, Kootenai CountyGas · 203 MW · withdrawn
- Gas project TCS-13, Kootenai CountyGas · 200 MW · withdrawn
- Battery storage project 117, Kootenai CountyBattery storage · 200 MW · withdrawn
- Gas project 109, Kootenai CountyGas · 200 MW · withdrawn
- Battery storage project TCS-17, Kootenai CountyBattery storage · 200 MW · withdrawn
- Other project CS23-07, Kootenai CountyOther · 12.1 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem