United States βΊ Grid βΊ Interconnection queues βΊ Idaho
GAS Β· WEST500MW Taft-Bell
500MW Taft-Bell is a 500 MW gas request withdrawn in the West interconnection queue, in Kootenai County, Idaho, connecting to Cogentrix Energy, Inc..
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2000 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G16
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Cogentrix Energy, Inc.
- Developer
- Cogentrix Energy, Inc.
- Connection point (POI)
- BPA's Taft-Bell 500 kV line in the vicinity of Kootenaid County, ID
- Location
- Kootenai County, Idaho
- Technology
- Gas: 500 MW
- Total requested
- 500 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 22 December 2000
- Proposed online date
- December 2004
Location
Marker shows the centre of Kootenai County; the queue data does not give exact sites.
Other requests in Kootenai County
- Hydro project Q63, Kootenai CountyHydro Β· 26.0 MW Β· agreement signed
- Hydro project 63, Kootenai CountyHydro Β· 26.0 MW Β· agreement signed
- Gas project CS25-05, Kootenai CountyGas Β· 102 MW Β· in study
- Gas project CS25-04, Kootenai CountyGas Β· 102 MW Β· in study
- Battery storage project C2-19, Kootenai CountyBattery storage Β· 1,800 MW Β· withdrawn
- Kootenai GenerationGas Β· 1,300 MW Β· withdrawn
- Gas project CS24-05, Kootenai CountyGas Β· 203 MW Β· withdrawn
- Gas project TCS-13, Kootenai CountyGas Β· 200 MW Β· withdrawn
- Battery storage project 117, Kootenai CountyBattery storage Β· 200 MW Β· withdrawn
- Gas project 109, Kootenai CountyGas Β· 200 MW Β· withdrawn
- Battery storage project TCS-17, Kootenai CountyBattery storage Β· 200 MW Β· withdrawn
- Other project CS23-07, Kootenai CountyOther Β· 12.1 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem