United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

BATTERY STORAGE Β· WEST

Battery storage project 117, Kootenai County

Battery storage project 117, Kootenai County is a 200 MW battery storage request withdrawn in the West interconnection queue, in Kootenai County, Idaho, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
117
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Rathdrum 230kV Station
Location
Kootenai County, Idaho
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
16 June 2021
Proposed online date
December 2025

Location

Marker shows the centre of Kootenai County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Kootenai County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem